Makes subtasks rescheduled when a 'precedes' relation is set on a parent task.
git-svn-id: svn+ssh://rubyforge.org/var/svn/redmine/trunk@3574 e93f8b46-1217-0410-a6f0-8f06a7374b81
This commit is contained in:
parent
8e3d1b694a
commit
d550c46160
|
@ -431,7 +431,24 @@ class Issue < ActiveRecord::Base
|
|||
end
|
||||
|
||||
def soonest_start
|
||||
@soonest_start ||= relations_to.collect{|relation| relation.successor_soonest_start}.compact.min
|
||||
@soonest_start ||= (
|
||||
relations_to.collect{|relation| relation.successor_soonest_start} +
|
||||
ancestors.collect(&:soonest_start)
|
||||
).compact.max
|
||||
end
|
||||
|
||||
def reschedule_after(date)
|
||||
return if date.nil?
|
||||
if leaf?
|
||||
if start_date.nil? || start_date < date
|
||||
self.start_date, self.due_date = date, date + duration
|
||||
save
|
||||
end
|
||||
else
|
||||
leaves.each do |leaf|
|
||||
leaf.reschedule_after(date)
|
||||
end
|
||||
end
|
||||
end
|
||||
|
||||
def <=>(issue)
|
||||
|
|
|
@ -73,9 +73,8 @@ class IssueRelation < ActiveRecord::Base
|
|||
|
||||
def set_issue_to_dates
|
||||
soonest_start = self.successor_soonest_start
|
||||
if soonest_start && (!issue_to.start_date || issue_to.start_date < soonest_start)
|
||||
issue_to.start_date, issue_to.due_date = successor_soonest_start, successor_soonest_start + issue_to.duration
|
||||
issue_to.save
|
||||
if soonest_start
|
||||
issue_to.reschedule_after(soonest_start)
|
||||
end
|
||||
end
|
||||
|
||||
|
|
|
@ -272,6 +272,21 @@ class IssueNestedSetTest < ActiveSupport::TestCase
|
|||
create_issue!(:estimated_hours => 7, :parent_issue_id => parent.id)
|
||||
assert_equal 12, parent.reload.estimated_hours
|
||||
end
|
||||
|
||||
|
||||
def test_reschuling_a_parent_should_reschedule_subtasks
|
||||
parent = create_issue!
|
||||
c1 = create_issue!(:start_date => '2010-05-12', :due_date => '2010-05-18', :parent_issue_id => parent.id)
|
||||
c2 = create_issue!(:start_date => '2010-06-03', :due_date => '2010-06-10', :parent_issue_id => parent.id)
|
||||
parent.reload
|
||||
parent.reschedule_after(Date.parse('2010-06-02'))
|
||||
c1.reload
|
||||
assert_equal [Date.parse('2010-06-02'), Date.parse('2010-06-08')], [c1.start_date, c1.due_date]
|
||||
c2.reload
|
||||
assert_equal [Date.parse('2010-06-03'), Date.parse('2010-06-10')], [c2.start_date, c2.due_date] # no change
|
||||
parent.reload
|
||||
assert_equal [Date.parse('2010-06-02'), Date.parse('2010-06-10')], [parent.start_date, parent.due_date]
|
||||
end
|
||||
|
||||
def test_project_copy_should_copy_issue_tree
|
||||
p = Project.create!(:name => 'Tree copy', :identifier => 'tree-copy', :tracker_ids => [1, 2])
|
||||
|
|
Loading…
Reference in New Issue